The front stairs are complete. We are getting close to the end of this ordeal/adventure. However I think that the guy that designed the front stairs has been watching too many Highlander movies.
This is intended to document the elevation of our house to 12.5 feet above the flood plain.
Friday, April 2, 2021
Saturday, March 20, 2021
Saturday, February 13, 2021
Saturday, January 30, 2021
Thursday, January 28, 2021
Saturday, January 23, 2021
Friday, January 22, 2021
Sunday, December 13, 2020
The brickers were supposed to be finished last week. Note that all that is left is the top of the tower on two or three sides. But rain on Friday kept them from finishing. They were going to come back Saturday and/or Sunday to finish, but Saturday was too wet from the Friday rain and it rained again on Sunday. So they are supposed to be here to finish on Monday, but I suspect it will be too wet from Sunday’s rain. The concrete guy was supposed to be here Monday, but he got put off till Tuesday. When the brickers can’t finish on Monday, then the concrete guy will get put off till Wednesday. Ad infinitum.
Tuesday, November 24, 2020
Saturday, November 14, 2020
Thursday, October 29, 2020
Sunday, September 20, 2020